Surfside is a small town with a hands-on review process. New homes and exterior changes go before a board, and building safety gets close attention.
Surfside has no separate design board. The Planning and Zoning Board reviews structures and site plans, and applications must be complete 30 days before the meeting.
Single-family and duplex projects need a pre-application meeting with the Town Planner. New homes and large additions need a property sign and mailed notices to neighbors.
Contractor registration runs on the Town's fiscal year and must be renewed by September 30.
Plans are submitted digitally, but the Town requires a final printed set before it issues the permit.
The Town's application number goes on the Miami-Dade, DERM and Fire submittals. Inspectors are part-time, so inspections are booked by request form or phone.
We prepare the board package and neighbor notice, keep your registration current, and coordinate the county reviews. Town Hall is at 9293 Harding Ave.